Major Road Construction Projects 2018

Road Construction Projects 

Please be aware that Draper City has two road construction projects that will affect SunCrest residents and cyclists. Cyclists will not be allowed on either road during the construction. We know that many of you use this road to commute, and for your safety we ask that you use another means of transportation. If you have questions on these projects, please cotnact Draper City's Engineering office at (801) 576-6369.
Reconstruction of Traverse Ridge Road from Suncrest Drive to Draper Heights Way. Storm drain pipe is being constructed on the uphill side. Uphill lanes are anticipated to be paved by mid August; traffic will then be switched to the uphill side and the downhill side will be closed for reconstruction. The anticipated project completion date is October 15. Bicycles and pedestrians are prohibited until the project is completed.

Traverse Ridge Road Construction Zone Cyclists Prohibited
Suncrest Drive Construction. Paving is complete. Finish items and striping are in progress. Anticipated completion date is July 1. Bicycles are prohibited until the project is complete.
Suncrest Dr Construction Zone

Construction of Lone Peak Parkway Connection from Golden Harvest to Ikea Way is underway.  
The anticipated opening date for this new roadway is early August with a full completion date of September 1.

12200 So Lone Peak Parkway Project.
This project involves storm drain installation and intersection improvements.  Realignment of the east leg of 12200 South is in progress.  Anticipated completion date is end of September.



13800 South Widening Phase 1. A short segment of 13800 South (from 647 E. to 693 E.) will be widened with curb and sidewalk on the north side. Tree removals are in progress. Two-way traffic will be maintained most of the time but occasional lane closures with flaggers will be necessary. Anticipated completion is mid July. Note: Phase 2 of this project (13800 South from 300 East to the Draper Canal Trail) is currently under design and is anticipated to be constructed in 2019. 

Highland Drive / New River Drive Intersection Project.
Re-grading and striping of the intersection is complete.  Landscaping and minor finish items are in progress.   Anticipated final completion date is July 15.

Pavement Maintenance Projects.
This Friday (June 7), slurry seal will be placed on Lone Peak Parkway from 12650 South to Golden Harvest Rd. and on Saturday slurry seal will be placed on Traverse Ridge Rd. from Highland Drive to Draper Heights Way.

Non-City Construction Projects


South Valley Sewer District (SVSD) – Sewer Main Replacement on Fort Street

Work on South Valley Sewer District’s sewer pipe replacement project on Fort Street from approximately 13400 South to Willow Springs Lane in underway. The anticipated completion date is mid-October. This project requires one-way traffic through the work zone that may cause minor delays, especially when school begins in August.

UDOT-Technology Corridor

UDOT will be adding two lanes in each direction to I-15 between Lehi Main Street and S.R. 92.  This work has begun and will continue until late 2020.  Although this project is not in our City, it will affect residences’ travel times when going south. 

UDOT Technology Corridor