Major Road Construction Projects

Detour Map of summer road construction projects

Suncrest Drive


Work is underway to reconstruct 3.2 miles of Suncrest Drive from Traverse Ridge Rd. to the Draper City limits. This project has an anticipated completion date of November 1. Two lanes of traffic will be open throughout the duration of the project. Traffic delays should be minimal. The speed limit has been reduced to 30 mph through the construction area and biking is prohibited through the construction zone.

Bangerter Parkway and 13800 South Intersection


The Utah Department of Transportation (UDOT) is working in conjunction with Draper City to improve the intersection at 13800 South and Bangerter Highway.  This project will provide an additional through lane for the north, west, and south legs of the intersection, as well as an additional left-turn lane on each of the north and west legs to improve mobility and travel times. Each leg will maintain one right-turn lane, and a raised median will be installed in the west leg to improve safety.  This project is under construction and is scheduled to be complete by the middle of October.

Construction barrels will be in place on all four legs of the intersection throughout the project to help guide traffic through the work zone.  Drivers should exercise caution as right turn pockets may be closed an lanes will be shifted and narrowed.  Please be aware of changing pedestrian conditions throughout construction - adhere to sidewalk closures and use designated alternate routes.

Crews will pour curb and gutter on the northeast quadrant of the intersection and will begin preparing the roadway for asphalt paving.  They will move west to begin roadway excavation on the northwest quadrant, adjacent to Harmons, as early as this week.  At that time, westbound 13800 South will have one through-lane open to traffic for up to one month as widening is completed on the west side.  

Significant traffic delays may be experienced in this area during construction.  To avoid delays, motorists are encouraged to plan extra time to travel through the intersection or avoid this area by using alternate routes when possible. Visit udottraffic.utah.gov for real-time traffic information or check the UDOT Traffic app before traveling through the area.  

This project will widen the intersection adding additional turning lanes and thru lanes to improve traffic movement.  It will include curb and sidewalk on 13800 South as well as reconstructing the pavement.  This project should be completed by the end of October.


Willow Springs Lane


Construction crews will remove and replace the failing asphalt pavement on Willow Springs.  The asphalt has deteriorated and has many potholes developing.  Replacing the asphalt will create a smooth, safe roadway.  

The west half of this project is nearly complete and the east half will begin after Draper Days.  Sections of the roadway will be closed during construction.  Notices of the closures and alternate routes will be provided prior to the closures.  The anticipated completition date for this project is August 12th.

13200 South - Boulter to Highland

 
Construction is underway to widen and extend 13200 South from the Draper Park Middle School to Highland Drive 13200 South is underway and should be completed by the end of September.  The road will be closed to through traffic during construction and motorists are encouraged to use alternative routes to avoid this area when possible. 

This project will connect the road from where it currently terminates on the west side of the UTA tracks to Highland Drive.  The existing road will be widened from Boulter Stree to Highland Drive, and  curb, gutter, sidewalk and a complete new roadway will be constructed.  

Connecting this road will add an additional east-west connection to the east side of the City.  This will reduce the congestion currently being experienced at the 1300 East and Pioneer Road round-a-bout and the 1300 East and Highland Drive intersection.  It will provide a more direct route for east side residents to the two schools located on 1300 East and 13200 South.  The addition of sidewalks will also make pedestrian access much safer.

Pioneer Road


Pioneer Road from 600 East to 700 East and portions of 700 East (north and south of Pioneer Road) will be widened and curb, gutter and sidewalk will be added through these areas. The asphalt pavement has deteriorated and needs to be replaced.  The addition of curb, gutter and sidewalk will improve storm water collection and provide for safer pedestrian movement.  

Crews are currently working on 700 East (south of Pioneer), which is closed to through traffic. Once 700 East is open to traffic, work will begin on Pioneer Road and Pioneer Road will be closed to through traffic. Notices of the closures and alternate detours will be provided prior to any closures.

Highland Drive Storm Drain


The existing storm drain in this area is deficient and does not adequately drain storm water when a large storm event occurs.  This project will install main line storm water collection piping for a section of Highland Dr. As part of the construction on 13200 South, storm drain will be added to Highland Drive (north of 13200 South).  This portion of Highland Drive will be limited to a single lane and one-way traffic will be controlled by temporary traffic signals.  Motorists should expect minor delays in traffic through the construction area.  The work on Highland Drive should be completed by the end of June.

Manilla Drive


Construction  to install a new storm drain line in Manilla Dr. and to reconstruct the road Manti Dr. to Traverse Ridge Rd. has been completed.  


Bangerter 600 west header 2

 

600 West Update - June 1, 2017

***

Project Completion

We are approaching completion of the Bangerter 600 West interchange project. Please be aware of intermittent lane closures over the next couple of weeks while crews complete the final details. Project completion date is weather dependent.

This will be our last email update. We thank you for your patience during the project. The hotline and email will remain active until the project is completed. Please let us know if you have any questions.

DSC00115

Intermittent lane closures still in place

Ongoing Work

▪ Installation of sidewalks
▪ Construction of curb and gutter on interchange ramps
▪ Installation of fencing
▪ Installation of road signs and pavement markings
▪ Landscaping

Installation of sidewalks

Construction of curb and gutter on interchange ramps

Installation of fencing

Installation of road signs and pavement markings

Landscaping

DSC00100

Northbound 600 West with new sidewalk

Lane Changes on Bangerter

▪ All lanes will be open during peak travel times
▪ 6 am to 9 am - Monday to Friday - eastbound
▪ 4 pm to 7 pm - Monday to Friday - westbound
▪ 12 pm to 4 pm - Saturday - eastbound and westbound (excluding some weekends as noted) Lanes will be reduced by 1 or 2 lanes in each direction during off-peak travel times.

All lanes will be open during peak travel times

6 am to 9 am - Monday to Friday - eastbound

4 pm to 7 pm - Monday to Friday - westbound

12 pm to 4 pm - Saturday - eastbound and westbound (excluding some weekends as noted) Lanes will be reduced by 1 or 2 lanes in each direction during off-peak travel times.

Project Details

▪ A grade separated interchange has been installed at 600 West. Bangerter Highway was raised approximately 12 feet to cross over 600 West.
▪ Right turns will still be accessible at 200 West
▪ The new interchange will tie in to local roads on the north and south sides of Bangerter to improve access to local destinations

A grade separated interchange has been installed at 600 West. Bangerter Highway was raised approximately 12 feet to cross over 600 West.

Right turns will still be accessible at 200 West

The new interchange will tie in to local roads on the north and south sides of Bangerter to improve access to local destinations

What to Expect during construction

▪ Traffic and pedestrian detours
▪ Noise
▪ Vibrations
▪ Dust
▪ Business access will be maintained

Traffic and pedestrian detours

Noise

Vibrations

Dust

Business access will be maintained

Work Hours

Crews will be working 24 hours a day, 7 days a week

IMG 9299

Crews working on final details of the project

Questions or Comments

Please let us know if you have any questions or comments.
Thanks!

600 West Interchange Team
801-649-5476
bangerter600west@utah.gov
udot.utah.gov/bangerter600west