Major Road Construction Projects - 2020

If you have questions on these projects, please contact Draper City's Engineering office at (801) 576-6369 or email engineering@draper.ut.us.


Highland Drive Reconstruction

Work began in June to widen and reconstruct Highland Drive to five lanes from Minuteman Drive to Bangerter Parkway. Curb and gutter has been installed on the north side of the roadway. The south side of the road is now being reconstructed. It is anticipated to be completed by October 5, 2020. Drivers should continue to expect lane reductions and lane shifts in the work area. Please note that the dedicated right lane from eastbound Highland to southbound Traverse Ridge Road will be reinstalled when the road work is finished. Questions or comments? Email eric.lundell@draper.ut.us or call 801-576-6365.

Lone Peak Parkway (11400 S. to 12300S.)
A small section on the southeast corner of the Election Rd intersection remains to be widened in late August/early September. Slurry Seal and re-striping of the northern half (from Election Rd to 11400 South) to add a second southbound lane will take place in September. Widening of the east side of Lone Peak Pkwy north of Election Rd remains on hold pending property acquisition but some utility work will proceed in that area through the Fall season.

Oak Vista Water Line / Road Reconstruction The waterline reconstruction is completed. The contractor is currently working on the reconstruction of the roadway. It is anticipated to be finished by the end of September.

Traverse Ridge Storm Drain Rehabilitation 
This project is to make improvements to the storm drain infrastructure. Work is expected to begin the week of August 24, 2020. Work will take place along Traverse Ridge Road down hill of the Woods Landing Court Intersection. Drivers should anticipate road closures and lane shifts. Work is expected to go until mid November, work in the roadway is anticipated to be complete by the beginning of October. Lane closures could occur from Oct. 9 - Oct. 27. More info here.


UDOT Projects

Draper City does not have control over UDOT (state transportation) projects. A summary of UDOT projects in Draper is provided below with links to UDOT's website for more information.

UDOT I-15 Northbound in Draper, Sandy and Midvale UDOT is adding a new general purpose lane from Bangerter Highway to 9400 S. and a collector-distributor system from 9400 South to I-215 to increase mobility and reduce congestion. Construction began summer 2019 and expected to be complete by late 2020. In Draper, road construction can be seen at State Street and Minuteman Drive. Visit UDOT to view latest updates.

UDOT 12600/12300 South; Creek Meadow Road to State Street UDOT has begun work to resurface, improve smoothness and extend the life of the roadway on 12600/12300 S. from Creek Meadow Road to State Street. ADA ramps and concrete work will be updated as needed. Day and night construction activity up to 6 days per week anticipated from May through August 2020. To view the latest updates, visit UDOT's website, email 1600south@utah.gov, or call the hotline 855-740-8740.


Other Upcoming Projects


Draper Elementary Access Road Draper City and the Canyons School District are working on a second access road to the Draper Elementary School, 1080 E. 12660 South, so that there will be two exit / entry points. Currently, the only access to the school is from the west, off of Fort Street. This single access point limits traffic circulation and flow at the school, and the backup of traffic extends out to and along fort Street. Having one way in and one way out can make it very difficult for emergency vehicles to respond to an emergency.

The new access road will connect the existing 12650 South roadway to Manfield Way (east of the school). This will provide a secondary access point to significantly improve traffic flow during the school’s drop-off and pick-up times as well as during an emergency. Overall, it will provide a safer place for the children to attend and the teachers to work. 

The majority of the new roadway will be constructed along the entire north end of the school on property owned by Canyons School District. This will necessitate the construction of an additional parking lot on the school property to replace the existing parking area that will become part of the new roadway. Canyons School District and Draper City will jointly develop an inter-local agreement detailing the responsible costs for each entity. 

Construction of this new roadway started this past summer. Due to the scope of this project, the project will be completed summer 2020. If you have any questions about this project, please contact Eric Lundell, Draper City, at (801) 576-6365. 

13490 South and Vista Blvd. A new traffic signal will be installed at 113490 So. and Vista Blvd. Work will begin in the summer of 2020.

1300 East Widening Project 1300 East from Nashi to Wayne's World will be widened from two to three lanes. The project includes adding sidewalks and curb and gutter. The project will begin the summer of 2021.